Total Losses in Power Distribution and Transmission Lines-Part 2
(2) Non-Technical (Commercial Losses):
- Non-technical losses are at 16.6%,
and related to meter reading, defective meter and error in meter
reading, billing of customer energy consumption, lack of administration,
financial constraints, and estimating unmetered supply of energy as
well as energy thefts.
Main Reasons for Non-Technical Losses:
(1) Power Theft :
- Theft of power is energy delivered to
customers that is not measured by the energy meter for the customer.
Customer tempers the meter by mechanical jerks, placement of powerful
magnets or disturbing the disc rotation with foreign matters, stopping
the meters by remote control.
(2) Metering Inaccuracies:
- Losses due to metering inaccuracies are
defined as the difference between the amount of energy actually
delivered through the meters and the amount registered by the meters.
- All energy meters have some level of
error which requires that standards be established. Measurement Canada,
formerly Industry Canada, is responsible for regulating energy meter
accuracy.
- Statutory requirements5 are for meters
to be within an accuracy range of +2.5% and – 3.5%. Old technology
meters normally started life with negligible errors, but as their
mechanisms aged they slowed down resulting
- in under-recording. Modern electronic meters do not under-record with age in this way.
- Consequently, with the introduction of
electronic meters, there should have been a progressive reduction in
meter errors. Increasing the rate of replacement of mechanical meters
should accelerate this process
(3) Un metered Losses for very small Load:
- Unmetered losses are situations where
the energy usage is estimated instead of measured with an energy meter.
This happens when the loads are very small and energy meter installation
is economically impractical. Examples of this are street lights and
cable television amplifiers.
(4) Un metered supply:
- Unmetered supply to agricultural pumps
is one of the major reasons for commercial losses. In most states, the
agricultural tariff is based on the unit horsepower (H.P.) of the
motors. Such power loads get sanctioned at the low load declarations.
- Once the connections are released, the
consumers increasing their connected loads, without obtaining necessary
sanction, for increased loading, from the utility.
- Further estimation of the energy
consumed in unmetered supply has a great bearing on the estimation of
T&D losses on account of inherent errors in estimation.
- Most of the utilities deliberately
overestimate the unmetered agricultural consumption to get higher
subsidy from the State Govt. and also project. reduction in losses. In
other words higher the estimates of the unmetered consumption, lesser
the T&D loss figure and vice versa.
- Moreover the correct estimation of
unmetered consumption by the agricultural sector greatly depends upon
the cropping pattern, ground water level, seasonal variation, hours of
operation etc.
(5) Error in Meter Reading:
- Proper Calibrated Meter should be used to measure Electrical Energy. Defective Energy Meter should be replaced immediately.
- The reason for defective meter are
Burning of meters, Burn out Terminal Box of Meter due to heavy load,
improper C.T.ratio and reducing the recording, Improper testing and
calibration of meters.
(6) Billing Problems:
- Faulty and untimely serving Bill should be main part of non-Technical Losses.
- Normal Complain regarding Billing are
Not Receipt of Bill, Late Receipt of Bill, Receiving wrong Bill , Wrong
Meter Reading, Wrong Tariff, wrong Calculations.
How to reduce Technical Losses:
(1) Converting LV Line to HV Line:
- Many Distribution pockets of Low
Voltage (430V) in Town are surrounded by higher voltage feeders. At this
lower voltage, more conductor current flows for the same power
delivered, resulting in higher I2R losses.
- Converting old LV (430V) feeders to
higher voltage the Investment Cost is high and often not economically
justifiable but If parts of the LV (430V) Primary feeders are in
relatively good condition, installing multiple step-down power
transformers at the periphery of the 430 volt area will reduce copper
losses by injecting load current at more points (i.e., reducing overall
conductor current and the distance traveled by the current to serve the
load).
(2) Large Commercial / Industrial Consumer get direct Line from Feeder:
- Design the distribution network system
in such a way that if it is Possible than large consumer gets direct
Power Line from feeder.
(3) Adopting High Voltage Distribution Service (HVDS) for Agricultural Customer:
- In High Voltage direct service (HVDS)
,11KV line direct given to cluster of 2 to 3 Agricultural Customer for
Agricultural Pump set and employed small distribution Transformer
(15KVA) for given these 2 to 3 customer through smallest ( almost
negligible) LT distribution Lines.
- In HVDS there is less distribution
losses due to minimum length of Distribution Line, High quality of Power
Supply with no Voltage drop, Less Burn out of motor due to less voltage
fluctuation and Good quality of Power, to avoid overloading of
Transformer.
(4) Adopting Arial Bundle Conductor (ABC):
- Where LT Line are not totally avoidable
use Arial Bundle Conductor to minimize faults in Lines, to avoid direct
theft from Line (Tampering of Line).
(5) Reduce Number of Transformer:
- Reduce the number of transformation steps.
- Transformers are responsible for almost half of network losses.
- High efficiency distribution transformers can make a large impact on reduction of Distribution Losses
(6) Utilize Feeder on its Average Capacity:
- By overloading of Distribution Feeder Distribution Losses will be increase.
- The higher the load on a power line,
the higher its variable losses. It has been suggested that the optimal
average utilization rate of distribution network cables should be as low
as 30% if the cost of losses is taken into account.
(7) Replacements of Old Conductor/Cables:
- By using the higher the cross-section
area of Conductor / cables the losses will be lower but the same time
cost will be high so by forecasting the future Load an optimum balance
between investment cost and network losses should be maintained.
(8) Feeder Renovation / Improvement Program:
- Re conductoring of Transmission and Distribution Line according to Load.
- Identification of the weakest areas in the distribution system and strengthening /improving them.
- Reducing the length of LT lines by
relocation of distribution sub stations or installations of additional
new distribution transformers.
- Installation of lower capacity
distribution transformers at each consumer premises instead of cluster
formation and substitution of distribution transformers with those
having lower no load losses such as amorphous core transformers.
- Installation of shunt capacitors for improvement of power factor.
- Installation of single-phase transformers to feed domestic and nondomestic load in rural areas.
- Providing of small 25kVA distribution
transformers with a distribution box attached to its body, having
provision for installation of meters, MCCB and capacitor.
- Lying of direct insulated service line to each agriculture consumer from distribution transformers
- Due to Feeder Renovation Program T&D loss may be reduced from 60-70 % to 15-20 %.
(9) Industrial / Urban Focus Program:
- Separations of Rural Feeders from Industrial Feeders.
- Instantly release of New Industrial or HT connections.
- Identify and Replacement of slow and sluggish meters by Electronics type meters.
- In Industrial and agricultural Consumer adopt One Consumer, one Transformer scheme with meter should be Introduced.
- Change of old Service Line by armored cable.
- Due to Feeder Renovation Program T&D loss may be reduced from 60-70 % to 15-20 %.
(10) Strictly Follow Preventive Maintenance Program:
- Required to adopt Preventive Maintenance Program of Line to reduce Losses due to Faulty / Leakage Line Parts.
- Required to tights of Joints, Wire to reduce leakage current.
How to reduce Non-Technical Losses:
(1) Making mapping / Data of Distribution Line:
- Mapping of complete primary and secondary distribution system with all parameters such as conductor size, line lengths etc.
- Compilation of data regarding existing loads, operating conditions, forecast of expected loads etc.
- Preparation of long-term plans for
phased strengthening and improvement of the distribution systems along
with transmission system.
(2) Implementation of energy audits schemes:
- It should be obligatory for all big industries and utilities to carry out Energy Audits of their system.
- Further time bound action for
initiating studies for realistic assessment of the total T&D Losses
into technical and non-technical losses has also to be drawn by
utilities for identifying high loss areas to initiate remedial measures
to reduce the same.
- The realistic assessment of T&D
Loss of a utility greatly depends on the chosen sample size which in
turn has a bearing on the level of confidence desired and the tolerance
limit of variation in results.
- In view of this it is very essential to fix a limit of the sample size for realistic quick estimates of losses.
(3) Mitigating power theft by Power theft checking Drives:
- Theft of electric power is a major
problem faced by all electric utilities. It is necessary to make strict
rule by State Government regarding Power theft. Indian Electricity Act
has been amended to make theft of energy and its abatement as a
cognizable offense with deterrent punishment of up to 3 years
imprisonment.
- The impact of theft is not limited to loss of revenue, it also affects power quality resulting in low voltage and voltage dips.
- Required to install proper seal
management at Meter terminal Box, at CT/PT terminal to prevent power
theft. Identify Power theft area and required to expedite power theft
checking drives.
- Installation of medium voltage
distribution (MVD) networks in theft-prone areas, with direct connection
of each consumer to the low voltage terminal of the supply transformer.
- All existing un metered services should be immediately stopped.
(4) Replacement of Faulty/Sluggish Energy Meter:
- It is necessary to replacement of Faulty or sluggish Meter by Distribution Agency to reduce un metered Electrical energy.
- Required to test Meter periodically for
testing of accuracy of meter. Replacement of old erroneous
electromechanical meters with accurate Electro static Meter (Micro
presser base) for accurate measurement of energy consumption.
- Use of Meter boxes and seals them properly to ensure that the meters are properly sealed and cannot be tampered.
(5) Bill Collection facility:
- Increase Bill’s Payment Cells, Increasing drop Box facility in all Area for Payment Collection.
- E-Payment facility gives more relief to
Customer for bill Payment and Supply agency will get Payment regularly
and speedily from Customer.
- Effectively disconnect the connection
of defaulter Customer who does not pay the Bill rather than give them
chance to pay the bill.
(6) Reduce Debit areas of Sub Division:
- Recovery of old debts in selected cases through legal, communication and judicial actions.
- Ensuring police action when required to disconnect connection of defaulter Consumer.
(7) Watchdog effect on users.
- Users must aware that the distribution
Agency can monitor consumption at its convenience. This allows the
company fast detection of any abnormal consumption due to tampering or
by-passing of a meter and enables the company to take corrective action.
- The result is consumer discipline. This
has been shown to be extremely effective with all categories of large
and medium consumers having a history of stealing electricity. They stop
stealing once they become aware that the utility has the means to
detect and record it.
- These measures can significantly increase the revenues of utilities with high non-technical losses.
(8) Loss Reduction Programmed:
- The increased hours of supply to Agriculture and Rural domestic consumers have resulted in higher loss levels.
No comments:
Post a Comment